Traffic Management - Bull Lane & Little Bull Lane
Shedfield Recreation Ground & Pavilion - Project
The Parish Council is currently working towards bringing improvements to the Recreation Ground at Shedfield, as well as to the Pavilion, for the benefit of the whole community. Funding is being sought through the Football Foundation and WCC to augment Parish Council Funds. This includes some of the Community Infrastructure Levy paid by developers to help us develop our local communities. The Proposed plan can be found at the link below.
Starting School in September 2020

Traffic Management - Bull Lane & Little Bull Lane

Galliford Try are constructing a SW sewer in Bull Lane and Little Bull Lane commencing 14 October 2019 lasting for approximately 17 weeks.  To enable construction of the sewer they have agreed with Hampshire CC to implement a “rolling road closure” in these roads.  See traffic management plans for more information.  Traffic Management Plan (1) and Traffic Management Plan (2)

Sandy Hill Close SW Sewer works weekly look ahead:

W/C 2/12/19

Constructing inspection chamber in footpath between Little Bull Lane and Brooklyn Close.

Constructing pipe in footpath between Little Bull Lane and Brooklyn Close.

Completing construction of temporary road for traffic diversion.

W/C 9/12/19

Setting up temporary road closure Little Bull lane.

Implementing traffic diversion.

Undertaking trial holes to locate underground services in Little Bull Lane.

Construction of Inspection chamber in Little Bull Lane.

Backfill and open road over Christmas period.

W/C 16/12/19

Undertaking reinstatement works between Little Bull Lane and Brooklyn Close.

24 hour contact number 0208 947 4000 – quoting Sandy Hill Close SWS.